Total Environment In that Quiet Earth
Total Environment In that Quiet Earth is located on Off Hennur Main road in North Bangalore, a posh neighbourhood with tastefully constructed residences. Check out this home development that Total Environment Building System is selling on Bangalore’s Hennur Main road, 14.60 acres of land have been dedicated to the Project’s development. The current status of the Total Environment In that Quiet Earth is under construction. However, the completion year will be 2025. The available configurations include 2 BHK, 3 BHK, 4 BHK apartments, and 4 BHK villas. According to the floor plan, the size of the units is between 1431.0 and 2890.0 sq. ft. This property includes 4 towers and 560 units. With a well-developed social infrastructure that includes reputable schools, colleges, restaurants, hotels, and malls. So that it can comfortably accommodate your lifestyle preferences and practical demand.
Total Environment In That Quiet Earth has apartments and villas for sale. However, this society will be equipped with the necessary amenities and facilities to meet the needs and specifications of homebuyers. This housing society provides a variety of property alternatives available at different prices point, making it one of the best places to call home - and all within your means.
Project Highlights
3 open side luxurious properties
A good network to Thanisandra's main road
Bio-metric main door lock with additional control from the main console and sub-phone
The 3-bedroom H20 home is designed around the concept of a traditional Indian courtyard
Total Environment In that Quiet Earth Apartment L21
Apartment L21 has three bedrooms and a patio garden. However, this house has a foyer and three bedrooms that are all a good size and have bathrooms an office, a large living room, a dining room, a kitchen, and a utility room. In addition, there is also a 2,628 sq ft garden and terrace. However, this home was a wire-cut brick exterior not only but they are organic and developed character with time. Moreover, the deck and garden spaces are accessible via large sliding glass doors. The terrace garden outside and the living room resemble one another. A deck offers comfortable open seating that can be used all day.
USP
Three sides open apartments
Centralised heat pump in each unit
A hybrid central air-conditioning system with blower units in the bedrooms of each apartment
Location Advantages
Bilwshvale is a prime area with many attractions, work, and recreational options nearby. Check out a few:
Cratis Hospital is just 4.2 km away
The shopping complex is just 4.3 km away
Bishop Sargent High school is just 5.1 km away
Garden City University is just 6.3 km away
Channasandra Railway station is 6.8 km away
SH 104 P ad T layout is just 7.3 km away
Baiyappanahalli metro is just 11.1 km away
Jakkur Aerodrome is just 12 km away
Floor Plans & Price list
The following property possibilities are offered in various combinations by this housing society. You can view the price list and floor plans for the Total Environment In that Quiet Earth.
Features & Amenities
Total Environment In that Quiet Earth Bileshivale housing society has 4 towers with 26 floors
The project is spread over the 12.5 acres
This project offers three phases
In this project, there are 791 units
Project Specifications
In-depth Information About the Phase 1- Tower
Structural slab 39 is completed; internal units are being plastered
Structural slab 39 is completed, and internal plastering is in progress.
Tower 3 - Structural Slab 33 is complete, and Structural Slab 34 is in progress. The blockwork over structural slabs 14,15, and 16 is in progress.
Structural Slab 35 has been completed, and Structural Slab 36 is in progress
Villas
PCC completed 18 villas in Cluster 1 - Villas Foundation.
A total of 18 of the 18 villas have been rafted.
A total of 18 villas have been completed using structural slab 1.
The structural slabs for 18 villas have been completed.
Villas Foundation PCC completed 13 Villas
Raft completed for 13 villas
Structural Slab 1 includes the completed 13 villas
Structural Slab 2 completed for 13 villas
Cluster 3 includes the villa foundation PCC completed for 16 Villas
Raft completed for 16 Villa.
Structural slab 1: Completed for 16 villas.
Structural slab 2: Completed for 16 villas.
For 27 units, the grade slab has been finished, the masonry for 7 units is finished, and tree plastering projects are still going.
Amenities Enhance Your Living Experience
Badminton Court
Basement Car Parking
Billiards
Club House
Community Hall
Cycling Track
Earthquake Resistant
Gated Community
Gym
Jogging Track
Landscaped garden
Library
Health Facilities
Library
Party Area
Library
Outdoor games
Play area
Rain Water Harvesting
Steam room
Squash Court
Swimming pool
Table Tennis
Tennis Court
Toddlers Pool
Visitor Parking
Indoor
24Hrs Backup Electricity
Fire Alarm
Intercom
Winding-up Words
We hope, the above information is enough to know about the Total Environment In that Quiet Earth. For more queries, connect with us at +91 99307 72000.
For more detail, visit our website total environment.

No comments:
Post a Comment